How do I set dependencies and save a baseline?
Link activities with Finish-to-Start (or 3 other dependency types), then save a baseline to measure drift against later.
Setting a dependency
Dependencies are set per activity, not by dragging on the Gantt chart — look for the small dependency (link) icon next to each activity row.
- Click the dependency icon next to the activity that should come second.
- Under “Add a predecessor,” choose the activity it depends on from “Choose an activity…”
- Choose the dependency type: Finish-to-start (the default — the second activity can't start until the first finishes), Start-to-start, Finish-to-finish, or Start-to-finish.
- Click “Add.”
If the dates you've entered actually violate the dependency you just set — the predecessor finishes after the successor is supposed to start, for a Finish-to-start link — the dialog flags it with a visible warning rather than silently accepting an impossible schedule.
Saving a baseline
A baseline is a snapshot: once saved, it doesn't change, even as you keep editing the live schedule. That's what makes “are we behind?” answerable later.
- In the Baseline panel, click “Save baseline” (needs at least one activity first).
- Give it a Name — for example, “Contract baseline.”
- Click “Save baseline.”
Once you've saved one, select it from the “Compare against” dropdown to see variance — how the live schedule has drifted from that snapshot. See how delayed status and variance are shown.